| |
23 MAY 2002
I. It is submitted that in order to present the Appellants'
case adequately, it is necessary to refer by way of overview, to the way
in which the issues between the parties have arisen.
2. As indicated in the Summary:
a. the subject property is and was at all times material
a residential property occupied by a single dwelling house and owned
by the Appellants;
b. the Appellants purchased the subject property some 18 years
prior to registration.
3. Although not discussed in detail in the Summary, it is
unlikely to be disputed, that at the time of the hearing before Her Honour:
a. the physical condition of the 1952 extension had been
very poor for a number of years;
b. most of its original features had been destroyed or removed;
c. it was uninhabitable;
d. on any test, its future was uncertain.
4. All of these aspects were considered and discussed in
detail, in the Conservation Management Plan [AB4 C443] hereinafter referred
to as "the CMP", a document tendered in evidence on behalf of
the Respondent.
5. It was not in issue that the removal of the roof did
not cause or materially contribute to its poor condition.
6. Nor was it in issue that when the roof was removed, most
of its original features were worn out, or had been replaced with materials
which were significantly different from the originals.
7. It is submitted that it was open on the evidence, to
infer that if the 1952 extension were to be retained, there would be considerable
force in any submission that the roof would have to be completely re-built,
the critical question being whether and to what extent it would be practicable
to build it with the same materials used originally.
8. This aspect was dealt with in detail in the CMP [AB4
C519 et seq,].
9. It was not in issue that since 1999, the Appellants had
been assiduously seeking a permit for an "overall redevelopment strategy"
for the subject property, involving the future maintenance of the 1947
building, the demolition of the 1952 extension, and the construction of
new accommodation at the front of the subject property, and that:
a. this procedure was both appropriate and logical, having
regard to the Act;
b. the hearing before the Heritage Council of an appeal in relation
to a permit application for an overall redevelopment strategy, including
demolition of the 1952 extension, was fixed for 23 May 2001;
c. the decision of the Heritage Council, would be final, subject only
to the intervention of the Minister, pursuant to Section 78 of the Act.
10. The appropriateness and logic of that procedure was
discussed and recommended in the CMP [AB4 C527].
11. Under Section 73( 1 )(a) and (b) of the Act, the matters
to be considered in determining a permit application, include (it is submitted)
a "weighing" exercise, in which not only heritage interests,
but the reasonable or economic use of the heritage place, must be taken
into account.
12. Accordingly, it is submitted that it was a discretionary
consideration of considerable weight in this proceeding, that on the evidence
relating to the physical condition of the 1952 extension, and having regard
to the matters to be considered under Section 73( 1 )(a) and (b) of the
Act, all of which were considered and discussed in the CMP , there was
a real possibility that no point would be served by ordering the replacement
of the roof, because a permit might shortly be issued for:
a. the demolition of the 1952 extension;
b. its incorporation in some form or other, into an overall redevelopment
strategy.
13. It is submitted, that there was at least some evidence suggesting
that the real reason why the Respondent had issued this proceeding, was
that in his opinion the Appellants, by causing the roof to be removed,
had incurred an obligation to replace it, which he required the Appellants
to fulfill, before serious consideration would be given to an overall
redevelopment strategy, namely:
a. evidence suggesting that the Respondent had declined
to offer any advice to the Appellants with regard to the nature of an
overall redevelopment strategy which would be likely to be permitted;
b. the following statement, repeated in substance in consecutive permit
refusals: "Achievement of the brief in its present form is not
supported ahead of the retention and reinstatement of the 1952 extension.";
c. the suggestion, repeated in officer reports relating to permit applications,
that a Conservation Management Plan was needed, before proper or sufficient
consideration could be given to such applications.
14. Her Honour, at paragraphs 56 and 57 of her reasons,
[AB6 E4] declined to take such matters into account.
15. The Appellants must refer to the chronology of events
set out in the affidavits sworn by the Respondent, to meet any suggestion,
that this proceeding became necessary, either because:
a. the Appellants were to blame for the fact that as at
the commencement of the hearing before Her Honour, they had not already
obtained a permit to demolish the 1952 extension; or
b. that in some other way, they were unfairly or unreasonably seeking
to avoid their obligations under the Act.
16. It was not in issue between the parties that the physical
condition of the 1952 extension was not deteriorating so rapidly, that
there was no time to wait for the result of an appeal to the Heritage
Council.
17. In the CMP , the issue of demolition of the 1952 extension
was considered on the basis that as the building was unstable, it would
be reasonable to require it to be stabilized, if it were to be retained
as a useable part of the house, thus adding the cost and risks of stabilizing
procedures to the list of relevant considerations.
18. Her Honour [AB6 E23] concluded that although the future
of the slab was difficult to predict, on the balance of probabilities
reinstatement of the roof would not be futile, without, apparently, considering
whether it was reasonable to expect the Appellants to retain it in an
unstable condition. She does not appear to have considered whether it
would be reasonable to use it for residential purposes.
19. At paragraph 21, in the course of identifying the nature
of the discretionary considerations which should be taken into account,
Her Honour adopted a passage from the judgment of Dixon CJ in Klein v
Domus, in which reference was made to the "the scope and purpose
of the provision, and its real object" but "within that very
general statement of the purpose of the enactment", the "real
object of the legislature", to "leave scope ...to give effect
to her view of the justice of the case" .Her Honour referred to another
passage, from the judgment of Kitto J. in R v Anderson Ex p Ipec-Air,
in which His Honour adopted a passage from Sharp v Wakefield, describing
a discretion allowed by statute to the holder of an office as intended
to be exercised "according to the rules of reason and justice, not
according to private opinion; according to law, and not humour, and within
those limits within which an honest man, competent to discharge the duties
of his office, ought to confine himself'.
20. At paragraph 43, Her Honour adopted a passage from the
judgment of Dixon J in Swan Hill v Bradbury in which the "absence
of any definite rule for the exercise of the discretion" was explained
by reference to "infinite variety of facts which may present themselves"
in connection with statutes which attempt to "reconcile the exercise
and enjoyment of proprietary and other private rights with the conflicting
considerations which are found to attend the pursuit of the common good".
21. Her Honour based her decision on the following conclusions
in relation to considerations of relevance to the common good:
a. (paragraph 31) that as Mr. Clerehan had proposed the
items of work relating to the roof and the partition, she could assume
that those items would constitute a sufficient restoration of the 1952
extension to preserve its status as part of a heritage place,
b. (paragraph 42) that although the future of the slab is difficult to
predict, the items of work relating to the roof would not be futile, by
reason of the instability of the slab.
22. Her Honour then endeavoured to assemble a collection
of conclusions in relation to the enjoyment of private rights. She identified
the following matters, but did not conclude that they should be given
any or much weight:
a. (paragraphs 47,49, and 50) that various permit applications
were made
b. (paragraph 48) that no action was taken against the Appellants for
failing to comply with a Repair Order
c. (paragraph 55) that there was insufficient evidence to warrant the
conclusion that the Appellants could not afford to have the items of
work carried out
d. (paragraphs 57 and 60) that the CMP had no formal status, and no
overall redevelopment strategy had been put before her.
23. At paragraph 61 Her Honour confirmed that she regarded
the following categories of considerations as relevant:
a. the purposes of the Act~
b. the future of the concrete slab;
c. the position of the defendants as owners of the property.
24. It will be convenient to deal first with category ( c ), referred
to above, namely, the position of the defendants, or as they now are,
the Appellants.
25. It is submitted on the evidence, that the following
considerations referred to in Grounds 8 and 9, were relevant to the exercise
of the discretion and were ignored:
a. that at all times the Appellants were assiduously endeavouring
to obtain a permit for an overall redevelopment, and acting reasonably
in so doing;
b. that the conduct of the Respondent, in declining to assist them,
and declining to consider demolition until they replaced the roof, forced
them to make more than pone permit application, and to adopt a trial
and error basis;
c. that the Respondent declined to advise or assist them, notwithstanding
the publication of the CMP, in the circumstances set out in the consent
orders;
d. that the Appellants were not responsible for any delay, in the circumstances;
e. that in determining the various applications, the Respondent did
not seriously consider or take into account the issue referred to above
at paragraph 10(h) hereof;
f. that having regard to the attitude of the Respondent to their applications
for a permit to demolish the 1952 extension, the Appellants acted perfectly
reasonably in appealing to the Heritage Council;
g. that in all the circumstances Her Honour should have refused an order
at least until the decision of the Heritage Council on the appeal was
given.
26. Turning to the slab, it is submitted on the evidence
that the following discretionary considerations referred to in Grounds
8 and 9, relating to the slab, were ignored by Her Honour:
a. that as the 1952 extension was uninhabitable, the carrying
out of the items of work relating to the roof, would definitely be futile,
so far as the Appellants ' interests were concerned, and a waste of
money;
b. that having regard to the unpredictability of the future stability
of the slab, on the balance of probabilities it could not be said that
reinstatement of the roof would !!Q! be futile.
27. It is also submitted that Her Honour incorrectly gave
weight to the fact that she could not find or conclude, that reinstatement
of the roof would be futile.
28. Turning to the purpose of the Act, it is submitted on
the evidence that the following discretionary considerations referred
to in Grounds 8 and 9 were not taken into account:
a. that the items of work relating to the roof did not
result in reinstatement or restoration of the original roof, nor did
they support or contribute in any positive sense, to the heritage value
of the 1952 extension;
b. that the provisions of Section 168 do not require anything other
than reinstatement of the roof to the condition it was in prior to contravention.
29. It is also submitted that Her Honour incorrectly gave
weight:
a. to an assumption which, further, was not justified on the evidence,
that Mr. Clerehan was of the view that any of the items of work would
constitute a sufficient restoration of the 1952 extension, to preserve
its status as part of a heritage place;
b. to her finding that the purpose of the Act would be advanced by the
making of the order for the carrying out of the works listed in paragraph
19 of her reasons.
31. Grounds 1 to 7 inclusive, seek to criticize the relevance
and weight given by Her Honour" to the discretionary considerations
selected by her.
32. Grounds 8 and 9" seek to demonstrate the manner
in which" it is submitted" Her Honour should have exercised
her discretion.
33. The grounds are relatively detailed" and for the
purposes of this Outline" it may be sufficient simply to set out
the chronological detail" referred to in the grounds, which is for
the most part taken from the affidavits of the Respondent" and not
in dispute.
34. The critical chronological events were as follows:
| 1973 |
The
Appellants purchased and occupied the subject property in 1973. |
| 1991 |
It was not registered
until 1991" by which time it had been substantially altered and
extended, and was in poor condition. |
| 1999 |
It
is common ground that in 1999, the Appellants wished to upgrade the
living conditions and re-occupy the subject property , which had been
either uninhabited or let for several years. |
| 15 July 1999 |
On 15 July 1999, the Appellants
applied for a permit. The Appellants had been advised by their consultants
that the .952 extension was unstable; accordingly, as part of their
permit application, they informed the Respondent in detail of this"
and proposed that the 1952 extension be demolished" on the
ground that the physical condition of the building was so poor"
that:
i. restoration and stabilization would be impracticable"
and the expense unjustified;
ii. reconstruction using new materials would not result in a building
of sufficient heritage significance to warrant the such an exercise.
|
| |
The
Respondent refused the application. The Heritage Council, on appeal,
confirmed the Respondent's determination. In their reasons however,
neither demonstrated that they had seriously considered or decided
the issues raised by the above ground. The officer report relied on
by the Respondent, (Exhibit RT 12, AB3 C 49) and Ground 4 of the Respondent's
grounds of refusal (Exhibit RT 16, AB3, C66) seemed to indicate that
the Respondent would not even consider demolition, "... ahead
of the retention and reinstatement of the 1952 extension " or,
possibly, the preparation of a CMP. |
| 25 July 2000 |
On 25 July 2000, the
Appellants made 2 fresh applications for a permit, one proposing demolition
of the 1952 extension, the other proposing retention (Exhibit RT 36,
AB3 C221 ). |
| 25 July 2000 |
The
Respondent commenced this proceeding on the same day. |
| |
The Respondent determined both
applications (Exhibit RT 54, AB3 C284) in a manner which the Appellants
found unsatisfactory.
i. The Respondent again refused to permit demolition, this time
in Ground 2, stating that .."Achievement of the brief in
its present form is not supported ahead of the retention and reinstatement
of the 1952 extension", and again without a CMP [AB3 C276].
ii. The Respondent granted a permit for the proposal involving
retention of the 1952 extension, but on conditions which reserved
a number of critical issues for further consideration, and required
the preparation of a CMP .
|
| |
The
Appellants appealed against both determinations, to the Heritage Council. |
| 12 Feb 2001 |
On 12 February 2001,
before the hearing of the appeals, this proceeding came on for hearing
before Her Honour for the first time, together with a proceeding numbered
5090/2000, issued by the Appellants against the Respondent. |
| |
Pursuant
to orders made by consent (AB6 F 1 to F 4, inclusive) both proceedings
were adjourned, on terms pursuant to which the Respondent would have
a CMP (Exhibit RB 1 AB 4 C44 3 et seq. ) for the subject land prepared,
and, pursuant to paragraph 3 of the order in this proceeding, upon
compliance with the recommendations in the CMP , both proceedings
might be discontinued. |
| |
The recommendation
in the CMP , with regard to the 1952 extension was set out at page
75 (AB4 C527). It appears to have proceeded on the basis summarised
in the Introduction, at page ii (volume 4, page C450) as follows:
"It can now be concluded that, since it has been built
on recovered fill with an inadequate amount of stabilisation,
with an unusual for its time, and inadequate footings system,
the walls and reinforced concrete slab are currently in an unstable
structural condition. Further to this, the observed defects in
the walls and footings appear to be long standing and not the
result of the roof being removed in 1999. Stabilisation of the
existing footings and walls is deemed to be possible, but it would
involve substantial interventions and would be expensive, meaning
that the extant structure probably needs to be demolished"
|
| |
The recommendation
(AB4, C527) was as follows:
"Whether' reconstruction' is warranted is an
important issue and must be considered in the light of an overall
redevelopment strategy where an effective and balanced wholistic
(sic.) approach is taken to the site incorporating conservation
objectives and the need for amenity of the owners/occupant.'"
|
| |
The Respondent declined
to initiate any steps with regard to the recommendation. |
| |
The
Appellants, endeavouring to comply with the recommendation, prepared
their own overall redevelopment strategy , which they forwarded to
the Respondent as a permit application. They discontinued proceeding
number 090/2000, and withdrew their current appeals. |
| |
The Respondent however,
refused to discontinue this proceeding. |
| 29 Jan 2001 |
On
29 January 2001, he refused the application. |
| |
On 15 February 2001,
the Appellants appealed to the Heritage Council, and requested an
expedited hearing, having regard to the fact that this proceeding
had been re-listed for hearing on 5 March 2001. |
| |
In
response, the Heritage Council fixed the hearing for 23 May 2001. |
| 5 March 2001 |
On 5 March 2001, the
hearing of this proceeding commenced before Her Honour, the Respondent
having successfully opposed an application for an adjournment on the
ground that notwithstanding the appeal, the hearing should not be
further delayed |
23 MAY 2002.
C.W.PORTER
OWEN DIXON CHAMBERS WEST.
Craig Porter - Barrister
Room 1114
Owen Dixon Chambers West
525 Lonsdale Street
Melbourne 3000
Telephone: (03) 92257457
Fax: (03) 9225 7955
Email: craigporter@vicbar.com.au
|
|
 |